How was our product developed?
The first 1 MW pilot was built and tested at the MAN laboratory facility in Holeby, Denmark, during the period 2005-2008.
The results revealed both a high sulfur and high PM (Particulate Matter) trapping that spurred the decision to build and install a full scale 10 MW pilot onboard the vessel M/V Baru during 2009.
A 0.6 MW demonstration and research unit of latest version has been installed at the maritime research institute, MARINTEK, located in Trondheim, Norway. This unit will form an important component in research programs related to PM formation, behavior and trapping and also handling of other gases like NOX.
TEST RESULTS
PM mass trapping:
Measured and analyzed in Holeby 2005-2008
More than 98% SOX trapping:
The following shows a typical result from the full scale unit onboard M/V Baru